Oakwood Previous Page    OAKWOOD CONSTRUCTION PHOTOGRAPHY    Oakwood Home Page

The Oakwood Residence
A Nature Sanctuary
Miami, FL
                       
Thao's Pagoda

Oakwood Project Index
Click on the item below
            item description
  1 Oakwood Project Information Site Info, Building Info, Consultants and Contractors
10 Oakwood Project Description  Project Description & Owner's Statement
  20 Oakwood Illustrations Floor Plans / Elevations / Misc
50 Oakwood Photo Station Map Photo Station Map

51 Oakwood Photo Station #01 Photo Station #01

52 Oakwood Photo Station #02 Photo Station #02

53 Oakwood Photo Station #03 Photo Station #03

54 Oakwood Photo Station #04 Photo Station #04

55 Oakwood Photo Station #05 Photo Station #05

56 Oakwood Photo Station #06 Photo Station #06

57 Oakwood Photo Station #07 Photo Station #07
58 Oakwood Photo Station #08 Photo Station #08

59 Oakwood Photo Station #09 Photo Station #09
60 Oakwood Photo Station #10 Photo Station #10

61 Oakwood Photo Station #11 Photo Station #11
100 Oakwood Demolition Photos January 2010

110 Oakwood Construction Photos February 2010 to June 2010
112 Oakwood Construction Photos July 2010 to December 2010

114 Oakwood Construction Photos January 2011 to March 2011
116 Oakwood Construction Photos April 2011 to June 2011
118 Oakwood Construction Photos June 2011 to August 2011

120 Oakwood Construction Photos August 2011 to October 2011
122 Oakwood Construction Photos October 2011 to December 2011
124 Oakwood Construction Photos December 2011 to December 2011
126Oakwood Construction PhotosJanuary 2012 to February 2012
128Oakwood Construction PhotosFebruary 2012 to February 2012
130Oakwood Construction PhotosFebruary 2012 to March 2012
132Oakwood Construction PhotosApril 2012 to July 2012
134Oakwood Construction PhotosJuly 2012 to August 2012
136Oakwood Construction PhotosAugust 2012 to October 2012
138Oakwood Construction PhotosOctober 2012 to November 2012
140Oakwood Construction PhotosNovember 2012 to December 2012
142Oakwood Construction PhotosDecember 2012 to January 2013
144Oakwood Construction PhotosJanuary 2013 to February 2013
146Oakwood Construction PhotosFebruary 2013
148Oakwood Construction PhotosMarch 2013 to September 2013
150Oakwood Construction PhotosOctober 2013
152Oakwood Construction PhotosOctober to December 2013

154Oakwood Construction PhotosDecember 2013 to March 2014

156Oakwood Construction PhotosApril 2014 to July 2014

158Oakwood Construction PhotosAugust 2014 to December 2014
160Oakwood Construction PhotosApril 2014 to December 2014
162Oakwood Construction PhotosApril 2014 to December 2014
701In Memory of Suzanne SkeelDecember 2014
801 Topping Off Day June 14, 2011
901 Oakwood Miscellaneous Photos Miscellaneous Photos

904 Quan Yin Statue Photos Quan Yin Statue Photos

907 Chilin (Kirin) Statue Photos Chilin (Kirin) Statue Photos

Construction Photos (continued)  
Back to Previous Construction Photos from Feb 2010 to Jun 2010
112
July 1, 2010 Sun Room Pump Room
looking SSE
Concrete finishing crew
at Reflecting Pond
July 22, 2010
Looking South toward
Reflecting Pond #2
From Reflecting Pond #2
looking North
(Cistern on left)
View NNW from Master Bedroom
toward Reflecting Pond #2
July 22, 2010
In Cistern looking toward
infinity edge
View looking South in Cistern to area below Reflecting Pond #2 In Cistern looking North
(ladder is leaning against infinity edge (w/o glass installed)
of Reflecting Pond #1)
July 29, 2010
The "Ruins" about to be converted
into a useable "Accessory Structure" for storage and a BBQ area 
Masonry walls starting to rise up
out of the foundation
Another view of the Cistern
(looking NE)
 
July 31, 2010
Concrete cuts being outlined
for new square footings
Concrete cuts
for linear footing
Slab preparation
Peter inspecting progress at Accessory Bldg
(Hmmm?... wonder whats
he's designing?)
lookin' at me...
lookin' at you....
lookin' at me...
Remaining walls of
Accessory Bldg being prepared
for new walls and columns
August 4, 2010
The "Accessory Structure" is now
under construction. It will have a garden storage room and a BBQ area.
The walls and columns are coming up. Most of the foundation rough plumbing is now in place.
preparing trenches column steel block masons hard at work
block mason making
the wall straight and true
"love birds building their nest" the infamous Live Oak branch watching the walls rise
August 17, 2010 As the walls rise the views are rapidly changing .
August 17, 2010 . .
August 25, 2010
many walls are filled
solid with grout.
columns reaching for the trees more walls and columns 
September 2, 2010
Looking North toward Foyer/Entry 
Looking South toward hallway to MBR Looking SouthWest toward future location of Aquarium
Looking SouthWest September 8, 2010
Looking East to Sun Room
Looking ENE toward raised 
Breakfast Nook
September 14, 2010 Looking West from Sun Room
toward Living Room
A major column taking shape
September 17, 2010
Looking NW toward Study
Looking ENE toward
Sun Room / Pump room
Looking WNW toward Study
from Living Room
September 17, 2010 Looking West from Sun Room
toward Living Room
getting ready for pouring slab
forming the structural ceiling over "hurricane room"
September 20, 2010
a partial view of 
extensive  Live Oak canopy
the walls rise to approach the Live Oak Canopy View looking ESE
from BR2
September 23, 2010
Looking SW toward Study
from Living Room
One of the might Live Oak
branches that will be within
inches of the structure
A view looking into the residence from the Front Entry...
in future there will be a
grand glass staircase to
the  mezzanine

September 23, 2010
one of the really tall
columns being constructed
the crew working hard on constructing a large and
tall column
The steel reinforcing
for the "Big Beam"
September 23, 2010
an aerial view of the Pump
Room on the East side of the
Sun Room the "Big Beam"
to the left
BR2 off to left and the column
steel heading up for the
Flying Buttress
(a real working flying buttress)
A concrete pumping hose
being assembled along
Living Room floor for a pour o
n
the 24th... if the rains let up
Project Foreman Virgil troweling freshly poured concrete
at Media Room sill
Pouring Main Floor Slab Ahh, it's finshed!
(looking NW toward
Kitchen Nook)  
 

Second stage of pour of
thirty-three foot (33')
high column
Pouring "THE BIG BEAM"
in the Sun Room
Putting the finishing touches
on the Upper Pond
(over the Pump room)
at the East end of the Sun Room 
October 11, 2010
View looking East
in Studio
Steps to Dining Room from
Studio / Media Room
Door to Bathroom #2
(aka Hurricane Room)
October 13, 2010
Thao at West end
of Dining Room
The roof of the West Patio with framing for glass waterfall
(plumbing pipe in NW corner)
Looking East from Dining Room toward steps to Kitchen





October 21, 2010
facing NW outside the Studio
with forming and reinforcing for
the display platform
Looking North from the
Mezzanine level down to
the Breakfast Nook
An aerial view (West)
of Master Bath
slab formwork
------
A view looking East from
the mezzanine level
An aerial view of the platform
that will accept and support a
Quan Yin statue (weighing
14 tons). Behind the platform is a pond what will be the base of the waterfall behind the Quan Yin.
An aerial view looking West
toward the Mezzanine level.  Bedroom #2 is just to the left
on the ground level
October 26, 2010
Pouring concrete.
The man in the lift up high is remotely controlling
the concrete pump.
The Studio platform
being poured (looking East)
The Mezzanine slab
just after concrete pour




The West Patio 
beams being poured
The Studio looking SouthEast toward the front entry Aerial view of Master Bath
slab after pour
The SouthWest corner of the Mezzanine Looking NorthWest toward
the West Patio formwork.
Notice the trunk of a
Live Oak that is within
inches of the structure. 
Another pallet of CMU block
being lifted up to
the Mezzanine level
Block masons constructing
the North wall of the Conserviary
(formerly called the Sun Room...
formerly called the Aviary...
...it's a long story) 
The Master Bath recirculating shower slab and pump sump  A view of how closely the
Live Oak trunk approaches the structure. We don't think we could be much closer than this..
Approaching the East facade
The ladder is resting on the
beam over the pump room
An aerial view of
rhe Conserviary looking
toward the platform
for the Quan Yin statue
The view from the doorway entering Bedroom #2 looing SouthEast to where future curtain wall glazing will be installed,

October 29, 2010 (Left to Right)
Thibeaux Architecture President Thomas Thibeaux ;
Krips Construction Project Foreman
Virgil West ;
Owner, Developer, Designer
and Project Mgr
Peter Bromer
(photo by Project Architect
Keith Popiel)
View facing West looking down corridor to Conserviary The Krips Construction crew
(L-R)
Omar, Virgil Jr.,
Foreman Virgil Sr., (w/ silver mug) 
George, Eugenio and Salvador
A view looking West toward the Living room and Mezzanine In this view looing West,
you can see the near edge
of the Living Room
as it steps down to
the natural grade
of the Conserviary
This picture illustrates how the Live Oak tree canopy surrounds and embraces the building and provides ample shade 
New walls coming upNew column being formed
looking at the framed opening of the Master Vanity fixed glass window looking WSW Another view of the large
Live Oak trunk extending
over the West Patio
An aerial view of the West Patio after concrete has been poured and formwork stripped.
A view  from West of the Cistern looking East toward Master Vanity Looking North toward 
West Patio and future waterfall
Looking North at
Master Bath exterior
and Reflecting Pond #2
A wider view from the WestThe north wall columns
being formed


Looking West tward Sun Room
and one can see the
Quan Yin statue now in place
and soon to be in a
protective enclosure during remaining construction
some of the framing for the protective enclosure being staged prior to enclosure a view of the Quan Yin statue from 10' below. 




Krips Construction
Project Mgr Kevin doing
some concrete saw cutting 
bracing still in place
under statue until upper
beams and structure
are in place.
Looking SouthWest
at Sun Room with statue
being enclosed
2010-11-19
View looking North along West Patio and Cistern
Looking South
at West Patio
Looking toward NorthEast
corner of pump room
and statue can be seen
protected in plywood enclosure
Looking South through studio
at main entrance
View from BR #2
looking SouthEast
View  in MBR looking northerly toward Hall to Living Room

Looking up to opening that
will contain horizontal
glass pane for waterfall
Beams being formed
near a Live Oak branch 
Many concrete beams..
a lot of steel
2010-12-06
Trees and beams
Beams and trees Kevin doing some
concrete finishing
2010-12-08
The cantilevered deck
at Studio front
A joining of beams

A big beam...

 
----- ----- -----
----- ----- -----
----- ----- -----
2010-12-30
installing a lintel 
at the "Crow's Nest"
the intersection of
four critical beams
looking through the
Living Room
toward the west

keep an eye here as photos are updated weekly